Progress: $3,513,680.00
Growth Projects
Funding Status
Total Needed: $3,670,000
Needed: $156,320.00
Current Status
On March 16, 2023, a demolition crew took out three apartments to open the space for a choir room, instructor's office, music storage room, and four music practice rooms.
On April 26, staff, volunteers, and students participated in the groundbreaking ceremony.
In May, the stormwater system was installed.
On June 10, we received the green light to begin construction. On June 24, we began pouring the footer.
The last week of June, the masons laid block on top of the footer.
On July 8, a horizontal boring machine bored a small tunnel to connect water pipes and internet cables from the new building to the main building.
Early on July 14, the concrete crew poured the floor.
Framing commenced in the week of July 18.
The second story was framed on July 28.
Trusses were set on August 1.
The week of August 12, the exterior was wrapped, and shingles were put on the roof.
By August 19, the porch roofs and beams were installed.
Exterior windows and doors are installed, and the porch is ready for brickwork on September 16.
On October 1, the building is ready for insulation and drywall on the interior and for brick on the exterior.
By the end of October, brickwork is going on outside, and drywall inside.
Siding is going up on December 2.
On December 15, cabinetry was installed.
On January 20, carpeting is installed.
On April 15, 2023, we hosted an open house for the new bookstore, warehouse, and offices.
We are deeply grateful for the successful completion of the new Resource Group building! This expands the range of resources it provides for schools and churches.
Register today for an event or term!